ROAD SURFACE DRESSING ASSOCIATION

 

 

 

 


CODE OF PRACTICE

FOR SURFACE DRESSING

                                      ROAD SURFACE DRESSING ASSOCIATION

 

 

 

                                     

 

                                      CODE OF PRACTICE FOR

                                                SURFACE DRESSING

 

                                              

 

 

 

 

                                              

 

 

 

 

 

                                               Consultant Director and Secretary

 

                                      John Baxter

                                      Westwood Park

London Road

Little Horkesley

                                      Colchester

                                      Essex CO6 4BS

                                     

 

 

 

 

 

 


Ó Copyright RSDA 1993

     First Published

     Revised 2001

     Second Revision 2004

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
No part of this document may be

reproduced without the written permission

of the Road Surface Dressing Association

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


R S D A Code of Practice 2004

 

 


INDEX

 

1

Preamble

2

2

Defining the site and its characteristics

4

3

Determining the specification

4

4

Site information

4

5

Planning the execution of the work

5

6

Spraybars

5

7

Joints

8

8

Traffic management

9

9

Road preparation

12

10

Binders

12

11

Chippings and chipping storage

12

12

Chipping application

13

13

Rollers and rolling

14

14

Sweepers and sweeping

15

15

All plant

15

16

Method of working

15

17

Aftercare

16

18

Surface Dressing for Footways and Cycleways

17

19

Quality Assurance

19

20

Division of responsibility between the Highway Authority and the Contractor in standard contracts

19

21

End-product specification contracts

20

22

Type Approval Installation Trial (TAIT)

20

 

Appendix A – Checklists

22

 

Appendix B – Glossary

24

 

Appendix C – Changing the type of binder used in a spraying machine

33

 

Appendix D – References

34

 

Appendix E – Photograph

37

                                                                            


 

 

 

ROAD SURFACE DRESSING ASSOCIATION

 

Code of Practice for Surface Dressing

 

 

 

Foreword to Fourth Revision 2004

 

The European Standard for Aggregates BS EN 13043 was introduced in January 2004 and replaced BS 63 – 1 and BS 63 – 2 when these were withdrawn in June 2004. Accordingly the Aggregates Section of this Code of Practice has been updated to reflect the changes arising from the implementation of the new Specification and National Guidance Document PD6682 – 2.

 

A New Section giving guidance on the designing of surface dressing to minimise noise generation has been added. The guidance in this section is based on research carried out at the University of Ulster under the supervision of Professor Alan Woodside. The Association with financial support from the Highways Agency and the Road Emulsion Association Ltd commissioned this research. The Guidance Note has been prepared with advice from the following panel under my Chairmanship:

 

Richard Ellis                                                       Ringway Specialist Treatments

Peter Kinsey                                                                       Highways Agency

John Simpson                                                         Road Maintenance Services

Ian Walsh                                                                   CSS (Babtie Group Ltd)

John Williams                                                                      Highways Agency

 

A working party led by David Trowell has revised and updated the section giving guidance on the safe use of spray tankers.

 

Finally an editorial working party led by Paul Lewis has under taken a complete review of the Code updating all sections.

 

 

S Struthers

Chairman

July 2004   

 


 

2004 REVIEW OF CODE OF PRACTICE FOR SURFACE DRESSING

 

 

 


1     PREAMBLE

 

1.1      General

 

To the highway engineer, surface dressing offers a quick, efficient and cost-effective way of maintaining skid-resistant and waterproofing road surfaces.  To obtain the best results it is necessary to give careful consideration to a wide range of detail and to plan and design the work carefully.  The speed of the surface dressing operation and the short duration of time during which motorists are inconvenienced is also an important issue.

 

The purposes of surface dressing are to waterproof the road surface, to arrest disintegration, to provide texture, and provide a skid-resistant surface.  This latter quality can play a major part in accident reduction and was highlighted by the initiative of the Department of Transport in 1987 when the Minister introduced minimum mean summer SFC values for motorways and trunk roads.  The importance of surface texture as provided by surface dressing has been highlighted by TRL report LR 286, which stresses that texture depth is important under both wet and dry conditions.

 

The purpose of this Code is to identify the important aspects of the process, and to refer to other documents relating to good surface dressing practice.

 

1.2      Health, Safety and Environment

 

All those involved in preparing and executing surface dressing operations have a legal duty of care for the health and safety both of the operatives carrying out the works, and those who come into contact with the operation whilst in progress and during aftercare.

 

The planning and organising for health, safety and environmental issues must commence as soon as a surface dressing programme is envisaged.  The Construction Design and Management Regulations will apply to most surface dressing operations and therefore clients, designers and planning supervisors must plan and prepare the information and documentation necessary to inform the prospective contractors of the specific hazards identified on the various sites and the level of risk which is envisaged.  This must take into account the nature of the site, the materials to be used, the traffic management requirements and any special health, safety and environment issues that have become evident during the pre-tender stage.

 

The client should employ a competent contractor.  The procedure of selection can be carried out at tender list stage by a questionnaire.  Once the contractors have been selected, the Outline Health and Safety plan contained in the tender document should be detailed enough for the prospective contractors to take account of the health, safety and environment issues in their tender submission.

 

On the appointment of the Principal Contractor to carry out the surface dressing operations, it will be his duty to prepare a Detailed Health and Safety Plan of that particular contract or works.  This must itemise the methods to be employed to overcome the specifically identified hazards and risk reduction measures that will be in force on this contract.

 

Once the works commence the Principal Contractor has the control of health, safety and environment matters but liaison with the client, police and the general public on issues of congestion, diversions or closures must be ongoing throughout the contract.

 

The Principal Contractor has duties under other pieces of legislation to look after the health and safety not only of his own employees but of other persons who work alongside them and also of the passing public.  Written risk assessments must be prepared which can be used to identify control measures for both physical and chemical hazards.  The measures must form the Contractor’s safe systems of work which enhance the safe behaviour of the workforce as well as protect the general public during the various stages of the works.

 

Account must also be taken of environmental factors with pollution from fumes, noise and dust being the main concern during the work phase.  Disposal of waste and protection from spillage and contamination are other considerations when looking at the overall surface dressing activity.

 

1.3      Training

 

The design of surface dressing and its execution is dependent on a wide range of factors.  Many engineers and technicians have been involved with surface dressing, but only a limited number of them have had any formal training in the design, specification and execution of the work.  This lack of training often results in inappropriate selection of materials, unsatisfactory preparation, incorrect rates of spread and lack of traffic control and aftercare.  All these can lead to premature failure and increased costs.

 

A useful way of comparing the effectiveness of a dressing, or other maintenance work, is to express it in terms of a ‘cost life index’.  This is the cost per square metre of the work divided by the satisfactory life in years.  It provides a measure of the “value for money” which the highway authority is achieving.

 

A low ‘cost life index’ and “high value for money” is the result of high-quality work.  This requires that all personnel involved in any operation should be appropriately trained.  It is the Association’s view that this principle should apply to all personnel involved in surface dressing and is a requirement under ISO 9002.  The RSDA runs regular training courses details of which can be obtained from the Consultant Director and Secretary.

 

1.4             Quality Assurance.

 

The Road Surface Dressing Association continues its commitment to quality assurance and has been instrumental in producing the Sector Scheme for Surface Dressing which is number 13a in the series of Sector Scheme Documents.

 

The Sector Scheme Document, which was first published in 1998, is available on the UKAS website www.ukas.com .

 

The Sector Scheme Technical Advisory Committee is currently chaired by the Association's Consultant Director and Secretary, from whom further details are available.

 


1.5      Planning and Coordination

 

Careful and detailed planning before work commences is an essential element of successful surface dressing.  There should be close co-ordination between contractors and their clients at every stage, commencing with a pre-works meeting, the purpose of which is to ensure total understanding of the way that the programme will proceed.

 

Contract prices will be provided by contractors based on an indication of the likely size of the client’s programme.  Significant reduction in the size of the indicated programme will increase the contractor’s overhead costs per square metre of work undertaken and contracts should make provision for compensating contractors under these circumstances.  It is in the interests of both contractors and clients that the programme of works flows smoothly from site to site without the need to travel many miles for the purpose of dressing small areas of road.

 

2     DEFINING THE SITE AND ITS CHARACTERISTICS

 

Before any design, planning or dressing is undertaken, it is important to identify the lengths of road to be dressed and to draw up a schedule.  A clearly understandable system such as a line, arrow and job number on the road surface is recommended.

 

3     DETERMINING THE SPECIFICATION

 

3.1  The selection of the right type of dressing, size of chippings and rate of spread of binder is as important as the design of other engineering works.  Each site must be considered in the light of its unique characteristics, including the nature of surface, geography, volume and speed of commercial and other traffic using the section of road.  Advice on the design of surface dressing is contained in the fifth edition of Road Note 39 "Design Guide for Road Surface Dressing” (2002) published by TRL Limited, Old Wokingham Road, Crowthorne, Berkshire RG45 6AU.

3.2  The design considerations of surface dressing are particularly important in order that the dressing applied to the road surface is right for the circumstances in which it has to operate and the job it has to do.  This is equally the case if the design is done by the Client or Contractor.

3.3 In recent years, there has been a movement towards "End Performance Specifications".  End Performance Specifications transfer the responsibility for the design of the dressing to the selected contractor who is also responsible for the execution of the dressing and generally guarantees the dressing for a specified period of time.

 

3.4  Advice on "End Performance" and "Recipe" specifications can be found in clauses 922 and 919 respectively of the Highways Agency Design Manual for Road & Bridgeworks available from HMSO.

 

4          SITE INFORMATION

 

It is important that the person in charge of surface dressing operations on site fully understands the type and extent of the work required.  One way of achieving this is the preparation of a schedule and map indicating the sections of road to be dressed, the length and average width of each section, the area to be dressed, the type of binder, rate of spread of binder, size of chipping and location of chipping storage area – The Information Sheet. 

 


5     PLANNING THE EXECUTION OF THE WORK

 

In addition to compiling the site information, the person supervising the dressing may need to decide which width of spraybar and type of chipping machine to use and where joints are to be located.  Most modern equipment can operate in standard lane widths and, where possible, the equipment selected should be compatible so that the spraying width and chipping width at each pass are the same (see Section 6 – Spraybars, Section 7 – Joints, and Section 12 – Chipping Applications).

 

Unless they are made with proper care, joints can become weak points on any dressing.  For that reason, the number of joints made should be kept to a minimum.

5.1      On narrow roads, it is better to spray the whole width in one pass, after making appropriate arrangements for temporary diversions. Where wider roads are being dressed, there are also advantages to be gained by introducing traffic diversions while the work is in progress.  This causes minimum inconvenience to road users and separates traffic from the surface dressing operations.

 

5.2      Temporary diversions should not be introduced casually and will involve consultations between contractors and the highway authority.

5.3   Poor planning can result in low daily output, increased costs and public criticism.  The information sheet mentioned in paragraph 4 also enables supervisory staff to give proper consideration to the order in which various sections are dressed, the number of lorries required to haul chippings from storage sites and when and where additional binder deliveries are required.  Wherever possible, operations that result in a break in the spraying operation can be planned to coincide in order to minimise “down time”.  Such operations include moving from one site to another, transferring binder from one tank to another and heating the binder.

 

6               SPRAYBARS

 

Most modern tankers are fitted with adjustable spraybars enabling the distance across the spraybar to be varied, whilst in motion, to cater for any changes in road width.  This enables the spraybar to be operated from 0.1m up to its maximum width.

 

Adjustable spraybars come in two types:

 

1)     Expandable: These can be expanded to the particular width required.  Typical machines available in the UK have maximum widths of 4.0m – 4.3m.

 

2)     Extendable: These can be extended by bolting on extra sections.

Fixed width spraybars are available in several sizes, from 2.25m to 2.75m.  These are often mounted on smaller tankers and are ideal for narrow roads, particularly housing estates, where manoeuvrability is essential.  The spraying width is also variable from 0.9m upwards.

 

In order to achieve the desired rate of spray of binder, two systems of control are used:

 

1)     The driver uses a pre-calibrated chart to select the correct forward speed and drives to that speed as indicated on a special low-speed speedometer.


2)     The spraybar is equipped with automatic ground speed control with the operator pre-setting the required rate of spread and, the controller then electronically controls the forward speed of the machine.

Note: for the highest levels of accuracy demanded by Clause 922 (see section 21), automatic speed control is required.

As it is essential that the correct amount of selected binder is applied onto the road surface, it is also necessary to check that the spraybar is working correctly.  Member companies of the Road Surface Dressing Association are required to have all their spraybars tested by a NAMAS-accredited testing house at the beginning of each season.  Contractors will also undertake additional tests to BS 1707 to calibrate their spraybars for use with various binders.

 

BS 1707 requires spraybars to be tested in depots that are suitably equipped, where binder is sprayed for a given duration over test trays divided into sections, each of which is 50 mm wide.  A satisfactory spraybar will deliver the same amount of binder into each section (plus or minus 15% of the average) and a spraybar that does not achieve this standard requires either adjustment or replacement of jets.

 

6.1.1      Checking Output

 

Although a successful test result will show that any particular bar is capable of operating within the limits specified in the British Standard, checks should be made at the start of each day and during the day as appropriate, for example if there has been a long break in the continuity of the work, to ensure that the jets are continuing to operate satisfactorily.

 

Spraybars are fitted with either swirling or slot jets.  The output from any jet is affected by both the temperature of the binder and the spraybar pressure.  The rate of spread of binder on the road surface is additionally affected by the speed at which the spray tanker moves. 

 

Some machines are fitted with equipment that automatically adjusts the output from the spraybar to compensate for variations in the forward speed of the spraybar.  Filters are fitted in the pipework feeding binder from the tanker to the spraybar to prevent any solid material reaching the spraybar where it could cause the total or partial blockage of a jet.  It is essential that these filters are checked at the start of each day as well as during the work, particularly if a drop in pressure is observed during spraying.

 

For bars fitted with swirling jets, a site test indicating whether or not all the jets are operating correctly can be carried out as follows:

 

All the jets, with the exception of the two that are at the extreme ends of the bar, should be closed and the bar opened momentarily.  The tanker should then be moved forward about a metre and the process repeated, closing the end jets and opening the penultimate jets at each end of the bar.  This process should continue to be repeated progressively along the bar until all the jets have been operated. This should produce a pattern as indicated in Diagram 1 and the photograph in appendix E.


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Where all the jets are working properly each of the patches of binder on the road surface will be circular and of similar appearance.  Where a jet is partially blocked, the shape of the spray from that jet will be irregular.  It should be removed, cleaned and retested.  This test may not be appropriate for bars fitted with slot jets but where it is possible, the spray pattern from a blocked or misaligned jet is noticeably different from jets operating correctly.

 

On-site testing of transverse distribution can be carried out using carpet tiles or similar material.  In this test, tiles forming a continuous strip, the full width of the spray bar and taped together, are laid in the path of the spraybar.  For a spraybar operating correctly across its full width, the difference in the weight of each tile before and after spraying with binder should be similar.

 

Once it has been established that a spraybar is operating correctly in a transverse direction, longitudinal distribution is normally controlled by the vehicle’s forward speed.

 

The rate of spread of binder over any section of road can also be calculated by comparing the area of the section dressed with the amount of binder used as determined by dipp